Selecting materials by cost and availability

Pick the material that meets the need at a sensible cost and that you can actually get in time.

3.3.7b · 3 min read

  1. Work out the true cost

    Cost is the price per unit times the amount you need. Add extra for waste and for fixings, or the total will be too low.

  2. Batch size changes the sums

    Making many products needs a lot of material. A small price difference per square metre can become a big difference over a whole batch.

  3. Cost and availability

    Cost

    • Price per unit
    • Amount needed
    • Waste allowance
    • Fixings and finishes
    • Total for the batch

    Availability

    • Is it in stock?
    • Delivery time
    • Right size or thickness
    • Enough for the whole batch
    • Can it be reordered?

    Cost is about money. Availability is about getting it on time.

  4. Availability matters

    A material is only useful if you can get it when you need it. Check stock, delivery time and whether it comes in the size you need.

  5. Cost is not the only factor

    A cheaper material may be weaker, wear out sooner or look poor. A dearer one may suit the product better and last longer.

  6. Make a justified choice

    Give the figures, then say which material you pick and why. Link cost and Availability How easily a material can be bought in the right size, amount and time. to the needs of the product.

key terms

Unit cost
The price of one unit of material, such as £ per square metre or £ per metre.
Availability
How easily a material can be bought in the right size, amount and time.
Waste allowance
Extra material bought to cover offcuts and mistakes, often given as a percentage.
Batch production
Making a limited number of identical products in one run.

worked example

A school makes a batch of 40 stool seats. Each seat needs 0.12 m² of board. MDF costs £8 per m² and needs 25% extra for waste. Recycled plastic board costs £11 per m² and needs no extra for waste. Calculate how much cheaper the MDF is for the batch.

  1. 1Find the area for the seats: 40 × 0.12 = 4.8 m². This is the net area for both materials.
  2. 2Add the waste to the MDF: 25% of 4.8 = 1.2 m², so 4.8 + 1.2 = 6.0 m².
  3. 3Cost the MDF: 6.0 × £8 = £48.00.
  4. 4Cost the recycled board: 4.8 × £11 = £52.80, with no waste added.
  5. 5Subtract to compare: £52.80 − £48.00 = £4.80.

the answer: The MDF is £4.80 cheaper for the batch (£48.00 compared with £52.80), even though it needs 25% extra for waste.

the classic mistake

wrong: I just did area times price and forgot the waste. The bigger price is always the dearer material.

right: Nope. Waste means you buy more than the net area. A cheaper board can still cost more if you need lots extra, so work out both totals.

exam tip

calculate

Work out a numerical answer, showing the method (AO4).

Show every step, with units. One mark for the area, one for the waste, one for each cost, one for the difference. A right answer with no working can still lose marks.

how to make it stick

Cover the worked example, redo it with new numbers, then check. Say out loud why you added the waste.

test yourself

  1. (a) Calculate the cost of the pine board for one shelf. [1 mark] (b) Calculate the cost of the oak board for one shelf. [1 mark] (c) Calculate the material cost of the whole batch if pine is used, including fixings. [1 mark] (d) Choose pine or oak for the batch. Justify your choice using cost and availability. [1 mark]calculate · 4 marks
  2. The planter frame needs 2 lengths of 0.80 m, 2 lengths of 0.50 m and 4 lengths of 0.45 m cut from one section of timber. The timber is sold only in whole 2.4 m lengths. Pine costs £7.68 per 2.4 m length. Oak costs £12.24 per 2.4 m length. Calculate how much more it costs to make the planter frame in oak than in pine. Ignore waste from saw cuts. Show your working. [4]calculate · 4 marks
  3. A maker needs 12 shelf boards, each 600 mm long, 200 mm wide and 18 mm thick. Two options are available. Option A: pine boards, each 2400 mm x 200 mm x 18 mm, 9.60 pounds per board, collected free. Option B: one sheet of MDF, 2440 mm x 1220 mm x 18 mm, 28.50 pounds, plus 8.00 pounds delivery. (a) Calculate the total cost of Option A. (1) (b) Calculate the total cost of Option B. (1) (c) Calculate the percentage by which Option A is cheaper than Option B, to 1 decimal place. (1) (d) Give one reason other than cost why MDF might be chosen. (1)calculate · 4 marks